Click on Add New Timesheet or +sign to create a new Timesheet
Choose the Staff Name
Enter Type of the Project from Dayworks, Project and Variations
Select the Project Name
If the type is "Variation," you have the option to enter the variation name. However, for "Dayworks" type, there is no need to enter the project name.
Supervisor: Choose the Supervisor name
The Supervisor Field can be modified or deactivated. This capability is managed by enabling or disabling the "Allow Supervisor To Be Changed" option within the Timesheet Settings.
Enter the Date of the Timesheet, Start Time and End Time of the Timesheet
Under Task Done, Click on + Add New to add a new task
Choose the Task Name
Enter the Start time and End time of this task. Specify any break time if taken
Add Notes if required
Multiple tasks can be added under one Timesheet. Labour Hours, Payroll Hours and Costs fields will be calculated automatically based on staff charge etc.